Audit finds pre-election car park splurge favoured Coalition seats

The Morrison government's pre-election car park funding scheme favoured Coalition-held seats. Photo: AAP
An audit has condemned the Morrison governmentâs handling of a pre-election splurge on commuter car parks.
The $660 million national commuter car park fund was set up as part of the governmentâs Urban Congestion Fund, established in the 2018-19 budget.
By the end of March this year, just two of the car parks had been built out of 44 projects selected for funding.
âThe Department of Infrastructureâs administration of the commuter car park projects within the UCF was not effective,â the auditor-general found in a report released on Monday.
âThe approach taken to identifying and selecting commuter car park projects for funding commitment was limited in coverage and was not demonstrably merit-based.â
The audit found the assessment work underlying the departmentâs advice to award funding to the selected projects was ânot to an appropriate standardâ.
Of the project sites given the green light, almost two-thirds were in Melbourne â two and a half times the number located in Sydney.
This was despite Sydney being identified by Infrastructure Australia as having most of the nationâs congested roads.
As well, 77 per cent of the commuter car park sites were in Coalition-held seats.
The audit revealed that on the day before the government went into caretaker mode before the 2019 election there was an âexchange of letters between ministers and the prime ministerâ relating to 27 of the car park sites.
Six recommendations to fix the program have been taken up by the department.
Urban Infrastructure Minister Paul Fletcher said all of the governmentâs infrastructure decisions were âbased on an identified need in the communityâ and made in the context of existing federal, state and local government investment.
He said having taken over the portfolio in December 2020 he had sought a review of all projects under the Urban Congestion Fund.
âBy the end of 2022, 90 per cent of all packages are expected to be completed or under construction,â he said.
âIt is normal practice in the delivery of infrastructure projects for there to be a significant lead time between the announcement of the project and construction commencing.â
Labor frontbencher Andrew Giles, who called for the audit, said the results were shocking.
âThis is sports rorts on an industrial scale,â he said.
âThis program was always about buying votes, not addressing the real needs of suburban commuters.â
-AAP