NBN rollout behind schedule, documents show
It has been a rough month for the company building the National Broadband Network (NBN).
Politicians continue to use the nation-building project as a political football, and now a series of leaks have put the rationale for the program under question.
According to one leaked internal document, the NBN rollout has fallen well behind schedule, with construction completions to February reaching 29,000, against a target of 94,000.
⢠Windsor will shine a harsh light on Turnbullâs NBN
⢠How the NBN could boost GDP by two per cent
â˘Â Rocket carrying first NBN satellite blasts off
âAfter a delay of two years, they are now ready to start rolling out along the lines that they have been planning for all those years,â telecommunications analyst Paul Budde said.
âWe still havenât seen the actual rollout along those lines happening, but it looks like finally they are getting there.â
NBN Co refused to be drawn on what it called the âallegedâ internal documents, but said the project has met or beaten every key target for six quarters in a row.
It pointed to figures showing the service is available to 1.9 million homes, and 850,000 customers are already connected.
NBN Co chairman Ziggy Switkowski told ABCâs The Business the project had not fallen behind schedule.
âWe have a series of milestones that will see all of this completed in 2020. And we have a very, very strong management team led by the CEO Bill Morrow, who continues to meet all of the milestones that the board has set him,â he said.
Now the government is facing another challenge to its NBN plans: former federal independent Tony Windsor.
The challenger for the seat of New England said the NBN was one of the reasons he is re-entering politics.
âIt has to be fibre to the home, and Iâll fight to see that restored,â he said.
But while politicians continue to squabble over the NBN, outside observers are calling for a truce.
âItâs time to take the politics out of this game,â said Laurie Patton, CEO of Internet Australia, the peak organisation representing all internet users.
âWe need the government and the opposition to sit down and say âwhat is in the best interests of the country? What do we need if we are going to be a truly competitive innovation nation?'â
Concern fibre will be âunusableâ in decade
Prime Minister Malcolm Turnbullâs sales pitch for fibre to the node NBN was that it was cheaper and quicker to deploy than Laborâs fibre to the home plan.
But there are signs those arguments are coming unstuck.
Another leaked document shows the NBN has been trialling a thinner and cheaper fibre cable, which has cut the cost of fibre from $1200 to $600 per connection.
Mr Patton said it was time for the Coalition to consider an about-face, and embrace fibre to the home.
âIf we are going to be an innovation nation, how are we going to compete against countries that have already got internet speeds 100 times faster than ours?â he said.
âIn 10 to 15 years from now, that copper wire will be well and truly out of date and unusable.â
But Dr Switkowski said some of the media reporting of the NBNâs progress had been unduly pessimistic.
âSince those newspaper reports appeared two, three, four weeks ago, the progress in terms of copper has been fabulously fast. So I stand very confident that we are going to hit the milestones that we have had approved,â he said.
Telecommunications analysts are also warning the Coalitionâs multi-technology mix might leave the government with a white elephant when it comes time to privatise NBN Co.
A recent report by PwC estimates that while the NBN may cost $56 billion to build, it might only be worth $27 billion on privatisation because of its use of outdated technology.
âThey all then have to face the massive cost of upgrading the fibre to the node to a fibre to the home network,â Mr Budde said.
âSo the future price of the NBN for privatisation would look very bleak indeed if we stick to this fibre to the node network.â
But Dr Switkowski said the problems with reports like PwCâs is that they bundle together profitable and unprofitable parts of the business.
âIf this was a fully privatised enterprise, it would be run a bit differently and much more profitably but a quarter of Australia would not have a connection because you canât get there economically,â he said.
-ABC








